• Skip to main content
  • Skip to primary sidebar
  • Home
  • Construction Engineering
    • Civil Engineering Construction
    • Plain & Reinforced Concrete-II
    • Civil Engineering Estimation
    • Engineering Materials
    • Structural Engineering
  • Mechanics
    • Mechanics of Solids 1
    • Mechanics of Solids 2
    • Soil Mechanics 1
    • Soil Mechanics 2
  • Survey
    • Surveying and Levelling
    • Surveying and Levelling 2
  • Environmental Engineering
    • Environmental Engineering
    • Environmental psychology
    • Environment planning
    • Environmental Design
  • Water Engineering
    • Fluid Mechanics 1
    • Fluid Mechanics 2
    • Hydraulic Engineering
    • Irrigation Engineering
    • Engineering Hydrology
  • Misc.
    • Pavement and Foundation
    • Engineering Geology
    • Theory of structures
    • Design of Structures
    • Steel Structures
    • Research methodology
    • Transportation Engineering
    • Contact Us

Civil Engineering Terms

Easy and Understandable Terms Related to Civil Engineering

You are here: Home / Civil Engineering Practice / Calculation of Forward Pass | Early start/Early finish time

Calculation of Forward Pass | Early start/Early finish time

September 22, 2012 by admin Leave a Comment

Forward Pass

Forward pass is a schedule calculation that determines the earliest start and early finish time of the activities and the minimum project duration.

A forward pass through the logic network will yield this information:

  • The earliest time each activity in the network can start and finish.
  • The minimum overall duration of the project.

In performing forward pass calculation, all successor activities are started as early as possible. And Each activity is postulated to finish as soon as possible. This finish requirement yields the following equation:

Early finish of nth activity = Early start of nth activity + Duration of nth activity

Early start/Early finish time

Early start time (ES) of an activity is the earliest point in time, that an activity may start.

The starting point for performing a forward pass is the first activity in the network. In the case of first activity of the project, the earliest time they may start is zero ( the end of day 0 or beginning of day 1).

Calculation of early start/early finish

 If only one precedence arrow leads into an activity, then that activity’s early start time is the same as the previous activity’s early finish time. It means the early start time of the next activity will be the same as that of the early finish of the previous activity.

To determine the early start time, when more than one arrow leads in to its node. Select the largest early finish time of all activities at the tail of arrows. Logically, an activity cannot be start until all previous activities are completed. In this case, the equation of early start will be:

Early start of nth activity = Maximum early finish of all previous activities

Early finish time

The early finish time is the earliest time the activity may finish.

Add the duration of each activity to the early start time to compute early finish time.

Using this systematic procedure, compute all the early start and early finish times from the beginning activities to the finish of the project. This sequence will complete the forward pass.

Overall duration of the project

The overall duration of the project is the Early Finish (EF) of the last activity in the network.

Filed Under: Civil Engineering Practice

Reader Interactions

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Primary Sidebar

Sponsors

Recent Posts

  • Brick calculator | Brickwork calculation and brick estimation
  • Los Angeles Abrasion test | Test for road aggregates
  • Shuttering removal time of different structural members
  • Weight of steel bars per meter – Weight of steel bars formula
  • How to calculate quantity of mortar and its materials
  • Specifications of First class brickwork
  • Properties of first class bricks

Pages

  • About CivilEngineeringTerms
  • Contact Us
  • Privacy Policy
  • Submit your article or Ask any query

Categories

  • Articles
  • Civil Engg Construction and Graphics
  • Civil Engg Construction and Graphics
  • Civil Engineering Construction
  • Civil Engineering Estimation
  • Civil Engineering Practice
  • Construction management
  • Design of Structures
  • Engineering Geology
  • Engineering Hydrology
  • Engineering Materials
  • Environment planning and practice
  • Environmental Engineering 1
  • Environmental psychology
  • Fluid Mechanics 1
  • Fluid Mechanics 2
  • General Terms related to Civil Engineering
  • Hydraulic Engineering
  • Introduction to Environmental Design
  • Mechanics of Solids 1
  • Mechanics of Solids 2
  • Pavement and Foundation
  • Plain & Reinforced Concrete-II
  • Research methodology
  • Soil Mechanics 1
  • Soil Mechanics 2
  • Steel Structures
  • Structural Engineering
  • Surveying and Levelling
  • Surveying and Levelling 2
  • Theory of structures 1
  • Transportation Engineering
  • Water Resources & Irrigation Engineering

Site Stats

Copyright © 2023 · Magazine Pro on Genesis Framework · WordPress · Log in