Archive for the ‘Civil Engineering Practice’ Category

Steel bars weight per meter

Sunday, September 24, 2017 21:29 No Comments

Steel bars weight per meter Here is a list of mild steel bars weight.

This was posted under category: Civil Engineering Practice

How to calculate quantity of mortar and its materials

Friday, September 22, 2017 17:40 No Comments

How to calculate quantity of mortar and its materials ? Area of the surface multiply with the thickness gives the quantity of mortar for uniform thickness. This quantity is increased by 30% for filling the joints and to make up uniform surface of wall. It will give wet mixed mortar.

This was posted under category: Civil Engineering Practice

Machine mixing and slump of cement concrete

Saturday, March 18, 2017 19:42 No Comments

Machine mixing of cement concrete Following points must be kept in mind for machine mixing of cement concrete. Stone ballast, sand and cement to be pour into the cement concrete mixer. For example, for concrete of ratio 1:2:4 first four boxes of stone ballast, then two boxes of sand and then one bag of cement […]

This was posted under category: Civil Engineering Practice

Hand mixing of Cement Concrete

Sunday, March 12, 2017 13:17 No Comments

Hand mixing of Cement Concrete Following points must be kept in mind for hand mixing of cement concrete. Hand mixing of cement concrete should be done in masonry platform or iron sheet.

This was posted under category: Civil Engineering Practice

Types of Detailed cost estimate for construction

Saturday, October 20, 2012 12:36 No Comments

Types of Detailed cost estimate Types of detailed cost estimate are following:

This was posted under category: Civil Engineering Practice

Types and Methods of Rough cost estimate

Saturday, October 20, 2012 12:23 No Comments

Types of Rough cost estimate Rough cost estimates are of the following types.

This was posted under category: Civil Engineering Practice

Qualities of a good estimator

Saturday, October 20, 2012 12:11 No Comments

Qualities of a good estimator Estimator must have the following qualities: Estimator has ability to read

This was posted under category: Civil Engineering Practice

Definition of Estimate | Estimation | Need for an estimate

Saturday, October 20, 2012 12:04 No Comments

Estimate An estimate is an anticipated or probable amount of construction which is usually made before

This was posted under category: Civil Engineering Practice

Type of Construction contract | Lump sum contract

Friday, October 12, 2012 8:24 No Comments

Lump sum contract Lump sum contract is typically used in building construction projects in which quantities are exactly measured.

This was posted under category: Civil Engineering Practice

Float | Total Float | Free and Interfering float

Monday, September 24, 2012 11:29 No Comments

Float Float is an additional time available to complete an activity beyond the activity’s work duration. For example having 6 days available to do

This was posted under category: Civil Engineering Practice